The Select Board has adopted the 2018 Climate Action Plan (CAP) and a policy to prioritize planning to achieve zero emissions community-wide by 2050. CAP Strategy 3, Improved Transportation Options, prioritizes modes of transportation that do not rely on fossil fuels. These priorities include the following improvements on Beacon Street, one of five major through-fares in Brookline: 

•    reliable EV charging infrastructure: installing DC fast, Level 2 charging stations to support residential garage orphans, regional commuters, and visitors to our cultural and commercial districts

•    new EV car share:  providing 10 EV car share spots

•    more bike infrastructure: preparing a feasibility study to scope out a bike path on the median 

•    safer pedestrian access: obtaining State funding for Complete Streets projects

EV Charging and EV Car Share Investment 

This venture is a joint partnership of the Town of Brookline, Eversource Make-Ready infrastructure program, Electrify America Cycle 2 Investment, Greenlots, and Greenspot with support from the Town's EV Charging Study Committee and the State's Executive Office of Energy and Environmental Affairs. 

Contact  Todd Kirrane, Transportation Administrator

Project Specs

Pending Town review and Select Board approval

  • 10% of the 600 parking spaces along Beacon median will be upgraded by Eversource for EVSE make-ready
  • 10 spaces will have Level 2 ports for the public (2019)
  • 10 spaces will have EV car share + Level 2 ports (2019)
  • 3 spaces will have DC fast chargers for the public (Tesla compatible) (2019)
  • capital, operating, maintenance, and electricity costs assumed by private partners
  • possible profit share for the Town
  • commitment to participation in Brookline Green Electricity
  • opportunity scale up program
  • compatible with long-term capital projects, such as median bike path

Map  8 locations over a two-mile stretch 

  • St. Mary's (DCFC), St. Paul, Coolidge Corner (DCFC), Brandon Hall, Washington Square (DCFC), Dean-Tappan, Englewood, Cleveland Circle (Ayr Road)
  • Download Beacon Street EVSE project map

Timeline  Slated for 2019